3.3 Project Management
This section describes how project management practices need to be adjusted in support of Agile projects by first identifying common Agile practices and then describing how these management practices work in terms of scope, schedule and cost baselines for the project work.
An integrated project management plan (PMP) is developed for the Agile project to define the basis of all project work and how the work will be performed. It describes how the project will be executed, monitored, control and closed. From the Agile perspective, the performance measurement baseline is an integrated scope, schedule, and cost baseline for the software release project work maintained in the Product Backlog against which project execution metrics are used to measure and manage performance. The PMP describes the series of phases (themes, initiatives, and epics) the project passes through from initiation to closure. The PMP also describes the Agile development management approach; i.e. Agile iteration-based (Scrum/XP), flow-based (Kanban) or a hybrid model. Figure 1 describes the hierarchal structure of the Agile project work effort. Notice that this view of the project work hierarchy is similar to the WBS in predictive (Waterfall) projects.
One additional consideration is that the above hierarchy promotes a multi-team or "scaled" agile approach. While methodologies exist to support the scaling of agile (i.e. Scaled Agile Framework (SAFe), Scrum of Scrums, Disciplined Agile Delivery (DAD), etc), these will not be presented in this playbook but are a topic for further elaboration as an organization's agile process matures.
In Agile projects the requirements are defined by the organization's stakeholders and Product Owner with support from the Agile Team in the form of Epics, Features, user stories or PBIs that are maintained in the Product Backlog. Therefore, the project scope for an Agile project begins with the organization's governance process which commonly consists of a Configuration Control Board (CCB) that produces a high-level product backlog for a release consisting of a list of approved requirements defined in the form of epics, features and sometimes high-level PBIs.
The product owner then works with the Agile Inception Team to prioritize these items (epics, features, PBIs if applicable). The PMO can initially use the MoSCoW (Must Have, Should Have, Could Have, Won't Have this time) method to prioritize requirements.
Once the user stories and PBIs in the product backlog are defined, prioritized and the MVP determined, Agile estimating techniques can be applied to estimate the effort for each feature, sum up the effort for all the features in a project as well as determine which features would be part of which release. The PMO and development team are then able to forecast a schedule and cost for the release project. There are several gross-level estimation techniques used by teams using agile approaches such as Scrum, Kanban, and eXtreme Programming which include T-shirt Sizes (for Features), and Affinity Mapping.
T-Shirt Sizes. This estimation technique can be applied when providing a quick and rough estimation to a project feature. Here, the features are estimated in T-shirt sizes, ranging from XS to XL, which would be later converted to numbers, as per requirements. In this type of estimation, the estimators assign a size to each of the features. Points are assigned to the each of the T-Shirt Sizes using the Fibonacci-like format: 0, 1, 2, 3, 5, 8, 13, 20, 40, 100. These points are summed up and based on a rough estimate of how many feature points can get done within a time period by a normal agile team (note, the more detailed the refinement, the better the estimates).
The cost for the release is estimated by using the team's iteration average cost and multiplying it by the number of iterations estimated to complete the backlog. For example, the following formula to determine budgeted cost can demonstrate this estimation for the above example: (Team monthly cost (example: $15,000.00 per month) multiplied by the number of months/iterations (example: 5 months) = $75,000.00 + other expenses = forecast budgeted cost.
The above example is utterly simplistic and does not take into account the following factors: